It is one of New Zealand’s biggest building projects in recent years and it turned downtown Auckland into a giant demolition site, as wrecking crews erased 15,000m2 of retail space in less than six months.

The clearing of the 70-shop, three-level Downtown Shopping Centre to make way for Precinct’s $850 million Commercial Bay development was, for the thousands of Aucklanders who passed the site each morning on the way to work, was a rare spectacle to behold.

Elsewhere in Auckland, wrecking crews have been cleaning up the Hobson Street site of SkyCity’s new International Convention Centre, and in Christchurch, recent work includes the tearing down of the old Calendar Girls building in Hereford Street. The damage caused by last November’s earthquake has also resulted in several high-profile demolition projects in Wellington - 61 Molesworth Street office block and Queensgate car park.

Peter Ward, founder of Ward Demolition, said the process of tearing down Downtown Shopping Centre was incredibly technical, and involved a large amount of stripping by hand to deal with the asbestos found in one of the structures.

“Demolition is a critical component of large-scale commercial projects, and the technical challenges can often pose a significant risk to the success of the overall project,” he said.

Large-scale demolition work typically involves:
• Meticulous pre-planning;
• Investigation of the site and structure;
• Setting up scaffolding and protection barriers around the perimeter of the site;
• Services into the buildings being decommissioned and made safe;
• Stripping internal building materials;
• Engineers on site to ensure the structural integrity of adjacent structures.

The aim of every project is to demolish safely, cleanly and on time – and to cause as little disruption as possible for neighbouring structures and to have minimal impact on traffic.

When demolishing Downtown Shopping Centre, Ward Demolition had to be careful not to damage the two office towers that also occupy the block: the 17-storey Zurich House, which is home to NZX Auckland, and the 17-storey HSBC House.

Mr Ward said: “We had connectivity and tremor issues. Wind was also a challenge. When we were removing a platform close to one of the neighbouring buildings, it would have taken just one gust to send the platform crashing into it, but we didn’t break a window.

“It’s a lot harder to take down a structure in a tight space in a busy urban environment than it is in clear space. The risk of damage to neighbouring structures is greater, and traffic management becomes a job within itself.”

“We had to change techniques. For the asbestos, we had to hand-strip the building - you can’t just send in the bobcats. But once we’d removed the asbestos, the rest of the structure came down easily. In the last phase, we cleared some real estate fast.

“You pretty much start from the top and work your way down. At its most basic, demolition is just the law of gravity at work. Once you mess with a building, it falls. The boys make it look easy with all the cool toys we have.”

The biggest part of any demolition job is waste removal and recycling.

Some demolition companies recycle up to 95 per cent of the building materials, with much of the concrete waste products used for driveway rocks and road underlay.

Mr Ward said his company’s capacity to recycle large volumes of waste both on and off-site was critical to helping the developers meet their construction targets. Almost all of the material from Downtown Shopping Centre – 90 percent – was recycled.